Project calendar

Project calendar configurations define the calculation of task duration and estimation, and the overall duration of the project. 

Setting up a project calendar will not only help you to keep track of time and follow the schedule but also properly estimate the timing of project completion, its costs and required resources. 

A well-defined project calendar will include general days off, breaks and working hours. Thus, when you add tasks you can make more precise estimations on how long they will take based on the project calendar.

Learn here:

Setting a calendar when creating a project

You can define the working schedule for the whole project when you create a project. 

There, you can select working days and working hours. The most common example of a weekly work plan can be from Monday to Friday, 9 to 6, with an hour lunch break: 

Projects - Calendar - First set up.png

Note: Task start and end times can only be set within the established project working hours as defined in the project calendar. For example, if the project working hours are from 9 AM to 6 PM, you cannot set a task to start at 8 AM.

Projects - Calendar -project working hours.png

Configuring project calendar

If you have already created your project without setting the working schedule or need to change it, add holidays or exceptions, you can do it in Project Settings.

To do this, click on the Project Settings icon 1 in the top right corner and choose Change working week 2. 

Projects - Calendar - Change working week.png

In this window, you can always modify Working days 1 and Working hours 2 as well as add exceptions 4 to your working calendar: add, edit, and delete days off, non-standard working hours, etc. 

It is also possible to switch between Calendar and Table views 3 for your convenience and add exceptions either through Calendar or Table.

Projects - Calendar - Settings.png

Setting days off

If you prefer to work with a calendar view, select the day you want to specify certain exceptions for in your project calendar. 

In Days off, you can mark events like national holidays, for example, or any other.

1 Choose Day off

2 Introduce the title of the holiday

3 Select the date

4 Enable the Repeat option

5 Define the frequency of repetition if needed. In our case, it would be each year. 

Also, you have a possibility to choose whether the repetition will take place forever 6 or until a certain date 7. 

Once you are done, click on Apply 8. 

Projects - Calendar - Holidays.png

Setting custom days

In Custom days, you can set up a specific schedule for non-standard working hours, for example, or any other exception. The process is the same as for Days off. 

1 Choose Custom day 

2 Introduce the title

3 Select the appropriate date

4 Enable the Repeat option

5 Define the frequency of repetition if needed. 

Also, you have a possibility to choose whether the repetition will take place forever 6, whether this is a permanent schedule, or until a certain date 7. 

If this Custom day has a different schedule, click on Working hours to set working hours 8.

Once you are done, click on Apply 9.

Projects - Calendar - Custom days.png

If you prefer to work with a Table view, click on Add exception to add Days off or Custom days following the same steps as for a Calendar view. 

All exceptions will be displayed in the Calendar view in red (days off) and orange (custom days) colors. 

Projects - Calendar - View exceptions.png

Saving project calendar as a template

There is another possibility within the project calendar that is a real timesaver. You can once create a calendar defining all the national holidays and general exceptions, save it as a template, and use it afterward for every project you create.  

In the Templates section of Project Calendar, you can:

  • Save as template your current calendar;
  • Choose template from the ones you have saved; 
  • Go to template editor to create a new calendar template. 

Projects-Calendar-Save template.png