To set up integration with Jira, take note of the following aspects:

  • Make sure you have both GanttPRO and JIRA Cloud active accounts. Integration is possible only with the CLOUD version of JIRA. GanttPRO does not integrate with JIRA Software Server.
  • In GanttPRO, only an Account Owner, Account Admins and Enterprise users with a Custom role and corresponding permission have the possibility to configure integration between GanttPRO and Jira. Other users will only be able to use it once it is configured. 
  • In Jira, only an Account Admin has the possibility to configure integration with GanttPRO.

To connect your GanttPRO and JIRA accounts, follow these steps.

1. Open your GanttPRO account and click on the Account settings in the lower left corner of the page. Choose Integrations and API 1 and then click on Connect 2.

Jira integration-setup.png

2. Open your Jira account in another tab and click on the Settings icon 1 on the upper right corner of the page. There, choose Jira apps 2.

Jira integration-jira apps.png

3. After that, in the Application links 1 сlick on Create link 2.

Jira integration-Application links.png

4. In the next window, choose the Direct application link 1, and type jiraapi.ganttpro.com in the Application URL field 2. Click on Continue in this window and in the next one that will appear afterward.

Jira integration-Application links-URL.png

5. After that, you will see a window Review link. Type GanttPRO in the Application Name field 1 and click on Continue 2.

Jira integration-Edit-Application name.png

7.  Now, to configure the Integration settings, click on the three dots 1 and select Edit 2 for the link you have just created.

Jira integration-Edit.png

8. Choose the Incoming Authentication 1 and fill in the Consumer Key field, Consumer Name, Public Key, Consumer Callback URL.

Note that you can find and copy this information in Step 3, after you click on Connect in the Jira Integration section in your GanttPRO account. 

Jira integration-Configure.png

Once you add all the information in Jira, click on Save 2 and Close. In Step 3 tick I have created a Jira backup 3 to move to the next step.

Jira integration-Incoming authentification.png

8. Copy your Jira link from the address bar of your browser and enter it in Step 4 of Jira integration configuration in your GanttPRO account. Then, click on Verify.

Jira integration-URL Jira.png9. In the emerging window, click on Allow.

Jira integration-Allow button.png

10. To import your project from Jira, click on the + Create new project sign 1 on the left sidebar, then on Create a new project 2 and Import from Jira 3.

Jira integration-Import new project.png

Select the project from the list 1 and click on Import my Project 2.

Jira integration-Import my project.png

The following fields will be imported and synchronized:

  • Task name
  • Assignee
  • Start and end dates 
  • Date of creation/Creator 
  • Status
  • Priority
  • Issue Key

Please note: Data is synchronized between Jira and GanttPRO in both directions. This means that:

  • If you delete tasks or task groups (including subtasks) in Jira, they will also be deleted in GanttPRO.
  • If you delete tasks or task groups (including subtasks) in GanttPRO, they will also be deleted in Jira.