Effort allocation

Fixed duration and estimation

This option will help to manage the workload when you have fixed deadlines and labor units for each task, and they should remain fixed even if you assign a task.

To enable it, open Project settings and select Fixed duration and estimation 1 in Workload calculations. GanttPRO will distribute working hours between resources. 

Suppose that a task duration is 2 days and the estimation is set to 8 hours. With fixed duration and estimation, those parameters will not change, no matter how many people you assign to the task (examples 2 or 3) and what their working schedule is. 